The single-shield TBM is specified for complex rock with uneven strata, fracture zones and a low groundwater table, where the side walls are too weak to take the reaction loads required by an open-type gripper machine. The shield protects the work area while segmental lining is installed inside it, which makes the configuration suited to ground that cannot support a gripper TBM.

Single-shield TBM

Working principle

A single-shield TBM is used in geological conditions where rock strength is weak and the side walls cannot react the loads produced by gripper shoes. During a drive, a rotating cutterhead equipped with disc cutters is pressed against the tunnel face to cut the rock, and chips fall away from the face into the muck system.

Unlike an open-type gripper machine, the single-shield TBM uses segmental lining as its primary rock-support method. Thrust cylinders push the machine forward by reacting off the most recently installed segment ring, and segment installation and excavation are carried out alternately rather than simultaneously: the machine advances one stroke, the ring is built inside the shield, and the next stroke begins.

Features

01

Cutterhead built with composite chromium-carbide wear-resistant plate and carbide cutter bits at the cutterhead edge for high wear resistance and long service life

02

Main drive on a double-row cylindrical roller thrust bearing for service life and safety

03

PLC control system with real-time monitoring and data acquisition

04

Multi-material transport system handles segments, pea gravel, consumables and other tunnel material

05

Cutterhead water-spray jets, dust extraction and air cooling reduce dust formation in the working environment

06

On-board drilling and grouting system available for ground reinforcement at unstable soft rock or fracture zones

Specifications

Excavation diameter6,880 mm
Length of shield + back-upAbout 104 m
Total powerAbout 2,260 kW
Main drive power1,540 kW
Maximum daily advance rate30 m
Maximum monthly advance rate546 m

Reference projects

  • Chongqing metro tunnel: first single-shield TBM in Chinese urban metro construction; 3.84 km section in sandy mudstone, sandstone and argillaceous siltstone; breakthrough November 2016, peak 30 m daily advance and 546 m monthly advance

    Location
    Chongqing, China
    Diameter
    6,880 mm
    Machines
    1
  • Fortezza Railway Tunnel (Verona-Fortezza link)

    Location
    Italy
    Diameter
    9,680 mm
    Machines
    2
    Configuration
    twin-tube double-track railway; 12.75 km bore per machine; 11th and 12th CRCHI exports to Italy

Applications

Single-shield TBMs are specified for complex rock with uneven strata, fracture zones and low groundwater, where segmental lining is required and a gripper TBM cannot react thrust into the side walls. The configuration suits urban metro tunnelling through mixed sedimentary ground, regional water-supply work in weak rock and any drive where a closed shield is needed for safety. CRCHI's principal public reference is the Chongqing metro section, the first single-shield TBM applied to urban metro construction in China.

Configuration and engineering

Every CRCHI TBM is engineered to project. Shield diameter, cutterhead geometry, drive power, segmental ring design and back-up arrangement are configured to the alignment, ground conditions and water pressure of the drive. Project-specific scope beyond the standard envelope is engineered to brief, and where a drive calls for it, a machine is developed from the ground up. CRCHI Australia is the engineering, commercial, commissioning and aftermarket point of contact for Australian projects.

Request a quote

Interested in the Single-shield TBM?

Contact our team for full specifications, project sizing, and pricing.