Pipe Jacking
Direct Pipe Laying Machine
The direct pipe laying machine pairs a slurry-balance TBM with a pipe thruster, with the pipeline welded to the machine tail and pre-laid for hundreds or thousands of metres before excavation begins. As the TBM advances, the pipeline is jacked continuously into the ground, so excavation and pipeline installation complete in a single pass with no in-tunnel pipe joining and no reception shaft.


Working principle
A direct pipe laying machine excavates the tunnel like a pipe jacking machine using slurry pressure balance for face support. The machine is built around two parts: a tunnel boring machine at the face and a pipe thruster at the launch side. The distinguishing feature is that the tail of the TBM is welded to the pipeline, which can be pre-laid for hundreds or even thousands of metres before excavation starts.
As the machine advances forward, the pipe thruster jacks the pipeline into the ground behind the TBM, so pipe installation never breaks the drive. When excavation finishes, pipe laying is finished too. A reception shaft is not required; the machine can also be retracted by the pipe thruster at any point, which keeps options open if obstacles are encountered or the drive needs to be aborted. A safe-thrust technology protects the anticorrosive coating on the steel pipeline, and a high-precision guidance system holds line and grade through to breakthrough.
Features
Pipeline welded to the machine tail and jacked continuously as the TBM advances, removing in-tunnel pipe installation steps
Continuous one-pass drives up to 1,000 m with peak advance to 100 m per day; field-proven 200 m bored in 2 hours without stoppage
Slurry-balance support method controls face pressure and limits ground settlement; the machine can be retracted by the pipe thruster if needed
Construction angle from -15 degrees to +15 degrees, suiting river crossings and grade changes that conventional jacking cannot reach
No reception shaft required, lowering surface footprint and overall project cost
Cutterhead configured per ground conditions, with safe-thrust technology that protects the anticorrosive coating on the steel pipeline
Specifications
| Bore diameters supplied | 1,300 mm and 1,505 mm (2 machines) | |
| Length (shield + back-up) | 14 m | |
| Total weight | 200 t / 270 t | |
| Maximum thrust | 5,000 kN / 8,000 kN | |
| Installed power | 770 kW / 820 kW | |
| Maximum advance rate | 5 m/min | |
| Construction angle | -15 degrees to +15 degrees | |
| Recorded performance | Continuous 200 m drive in 2 hours without stoppage |
Reference projects
Eastern China oil pipeline project
- Location
- Eastern China
- Diameter
- 1,300 mm and 1,505 mm
- Machines
- 2
- Configuration
- Continuously tunnelled 200 m within 2 hours without any failure; max thrust 5,000 kN and 8,000 kN; installed power 770 kW and 820 kW; total weight 200 t and 270 t; max advance rate 5 m/min; construction angle -15 to +15 degrees
| Project | Location | Diameter | Machines | Configuration |
|---|---|---|---|---|
| Eastern China oil pipeline project | Eastern China | 1,300 mm and 1,505 mm | 2 | Continuously tunnelled 200 m within 2 hours without any failure; max thrust 5,000 kN and 8,000 kN; installed power 770 kW and 820 kW; total weight 200 t and 270 t; max advance rate 5 m/min; construction angle -15 to +15 degrees |
Applications
Small-diameter water diversion tunnels, water drainage tunnels, oil and gas pipeline laying, and other long-distance pipeline installations where a single-pass trenchless drive is preferred to open-cut or shaft-based methods. The construction-angle range and continuous-drive capability suit river crossings, grade changes and long peri-urban pipeline runs across AU procurement scenarios that involve operational highways, watercourses or sensitive surface land. The published international reference is the Eastern China oil pipeline programme, where two CRCHI machines recorded a continuous high-rate drive without stoppage.
Configuration and engineering
Every CRCHI TBM is engineered to project. Shield diameter, cutterhead geometry, drive power, segmental ring design and back-up arrangement are configured to the alignment, ground conditions and water pressure of the drive. Project-specific scope beyond the standard envelope is engineered to brief, and where a drive calls for it, a machine is developed from the ground up. CRCHI Australia is the engineering, commercial, commissioning and aftermarket point of contact for Australian projects.
Related machines
Request a quote
Interested in the Direct Pipe Laying Machine?
Contact our team for full specifications, project sizing, and pricing.


